Analysis of Factors Influencing Time and Cost Overruns on Construction Projects in South Eastern Nigeria

Author(s)

K.A. Okorocha , S.C. Emeribe , E.C. Ubani ,

Download Full PDF Pages: 73-84 | Views: 379 | Downloads: 116 | DOI: 10.5281/zenodo.4916314

Volume 2 - February 2013 (02)

Abstract

This study identifies and examines the factors influencing time and cost overruns on construction project in the south eastern Nigeria. The high level of dilapidation and deterioration of roads and other construction infrastructural facilities seen in this zone could be attributed to abysmal performance of construction project management. Survey technique with area and random sampling procedures were employed for the study. The primary data were obtained with the instrument of weighted scaled questionnaires the respondents to the questionnaire are clients, contractors and consultants from five states of south eastern Nigeria. A total of 110 and 42 hypothetical cost and time overruns respectively were identify for analysis. The methods of data analysis were spearman’s rank correlation coefficient and Kendall’s coefficient of concordance with the hypothesis tested at 5% level of significant so as to determine the degree of agreement amongst the parties. The results of this study have shown that the three parties to a project are in agreement that materials factor and external factor groups have indeed contributed immensely to delays on construction projects, while projects, contractor’s responsibilities, consultant’s responsibilities, client’s responsibilities, professional management, design and documentation, execution, labour and equipment, contractual relationship, government relations, time overruns; cost overrun and all together (time and cost overruns) factors have not greatly influenced delays on construction projects. Based on these results it is recommended that client’s, contractor’s and consultant’s should pay more attention to both material and external factors for there to be effective and efficient delivery on construction projects at the right time and cost. 

Keywords

Time overrun, Cost overrun, Construction project clients, Contractors, Consultants, Spearman’s rank correlation coefficient, Kendall’s coefficient of concordance. 

References

                   i.            Achermann F., Eden C. and Williams T. 92005). Analyzing project cost overruns: Comparing the measured mile analysis and system dynamics modeling. International Journal of Project Management, Vol. 23, No. 2, pp. 135-139.

       ii.            Aibinu A.A. and Jagboro G.O. (2004). The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management Vol. 20, N0. 8, pp. 593-599.

     iii.            Al-Gahtani K. and Mohan S. (2007). Total float management for delay analysis. Journal of Cost Engineering. Vol. 49, No. 2, pp. 32-37.

     iv.            Assaf S. (2006). Causes of delay in large building construction projects. Journal of Management in Engineering. Vol. 11, No. 2, pp. 45-50.

       v.            Chimwaso K.D. (2006). An Evaluation of cost performance of public projects; case of Botswana. Department of Architecture and Building Services. Private Bag 0025, Gaborone, Botswana. Creative research systems. (2001). www.cdb.riken.jp

     vi.            Kessing S. (2010). Delay in joint projects. Report prepared in Freie University Berlin and European University Institute.

    vii.            Ogunlana S. and Olomolaiye P. (2005). Construction delays in a developing economy: Comparing Nigeria with other economics. International Journal of Project Management, Vol. 14, No. 1, pp. 37-45.

  viii.            Lo T., Fung I., and Tung K., 2006, Construction delay in Hong Kong civil engineering projects, Journal of Construction Engineering and Management, Vol. 132, No.6, pp. 636-649.

      ix.            Sambasivan M. and Soon Y., 2007, Causes and effects of delays in Malaysian construction industry, International Journal of Project Management, Vol.25, No.5, pp. 517-526.

       x.            Vidalis, M.S and Najafi, T.F., 2002, Cost and time overruns in highway construction 4th transportation specially conference of the Canadian Society for civil Engineering, Montreal, Quebec, Canada June 5-8(2002)

Cite this Article: